First Solar reported third-quarter 2026 net sales of $1.23 billion, a 58% gross margin and $571 million in net income, while lowering its full-year outlook as tariff uncertainty slowed module orders.
Net sales declined 23% year over year because the company sold fewer modules to third parties. Gross margin was about 20 percentage points above the same period in 2025, and net income increased 25%. First Solar also authorized a new $500 million stock repurchase program.
Lower full-year guidance
The company reduced its 2026 volume forecast to 16.0 GW to 17.0 GW. It now expects full-year net sales of $4.6 billion to $4.9 billion, down from the $4.9 billion to $5.2 billion range issued after the second quarter.
Management discussed the changes on its third-quarter earnings call, framing them against the August Section 232 tariff proclamation and a slower pace of customer purchasing. Executives also addressed the future of the company's 1.8 GW Malaysia factory, perovskite investments and the cost position of forthcoming modules built with its CuRe technology compared with crystalline silicon PERC and TOPCon products.
Project-specific contracts
First Solar ended the quarter with a contracted backlog of 44 GW valued at about $13.5 billion, with deliveries scheduled through 2030. Since its second-quarter update, it recorded 1.4 GW of U.S. bookings at an average selling price of about 36 cents per watt.
Despite slower bookings, CFO Alex Bradley said the company plans to avoid the spot market for international volume. Instead, it is moving toward project-specific contracts with defined delivery schedules, rather than the multi-year framework agreements covering multiple projects for very large customers that First Solar has used in the past. Bradley said project-based contracting supports more efficient operational planning and can reduce working capital requirements and warehousing costs, even if it slows the rate at which multi-year backlog is added.
Tariff pressures and Malaysia
CEO Mark Widmar described the Section 232 proclamation as a meaningful shift for U.S. solar manufacturing. He said nearly 80% of First Solar's global manufacturing footprint will be in the United States by 2027, and the company believes it is the only fully integrated utility-scale manufacturer without dependence on a Chinese crystalline silicon supply chain, leaving it structurally prepared to benefit from the new environment. That is a company assessment, not an established outcome.
Near-term procurement and price discovery have nevertheless slowed. Widmar said developers are holding back module purchases for 2029 and 2030 while they work through interconnection constraints and local opposition to data center deployment, await further guidance on Foreign Entity of Concern rules and assess how Section 232 minimum import prices and anti-stockpiling rules will be enforced.
The pressure is most acute for First Solar's international Series 6 production in Southeast Asia. Its Vietnam facility is slated to supply semi-finished Series 6 modules to a newly inaugurated South Carolina finishing plant, while the Malaysia factory continues to make finished international modules. Widmar said First Solar expects to make an all-or-nothing operational decision on the Malaysia plant in the first half of 2027: run it at full or near-full capacity, or shut production. Because Malaysian modules do not qualify for U.S. Section 45X manufacturing tax credits and face freight and tariff costs, the company does not expect either outcome to materially affect its run-rate earnings.
Technology and legal disputes
Before the call, First Solar announced a non-exclusive patent licensing agreement with perovskite company CubicPV, adding rights to its existing agreement with Oxford PV. The company plans to begin producing Series 6-form-factor perovskite modules for field testing and durability validation at its Perrysburg, Ohio, facility in the first half of 2027.
Management also commented on legal disputes over its TOPCon intellectual property and a warranty lawsuit filed by developer Swift Current Energy. Widmar said First Solar will soon file its formal legal response and maintained that its warranty terms govern any remediation. The company will support obligations under its limited-liability warranty, he said, but will not provide remedies outside those parameters.